What regulations should be considered in the appearance inspection of purification workshop

2022-08-29 08:17:18
times

After the completion of the purification workshop, one step in the project acceptance work is to inspect the architectural appearance of each location of the purification workshop. The construction unit, the contracting unit and the project construction supervision unit shall constitute the acceptance team, which shall carry out the project acceptance one by one for each project. The principle of purification room workshop purification is that when the control panel is connected to the switching power supply, the port of the oil mist separator causes strong negative pressure, which drives the welding soot to be sucked into the oil mist separator. The oil mist separator impacts under the effect of the impeller, so that the fine particles gather into controllable small particles, and the separation of gas and water is completed under the barrier of the high-efficiency fog absorbing raw materials. In addition to the inspection of appearance, inspection of engineering construction records, verification of design drawings, and change of engineering drawings, attention should also be paid to the coordination ability and executability of some adjustment machinery and equipment. In the inspection of appearance of purification workshop, there should be written records and the signature of the staff who have signed up for it.


The appearance inspection of purification workshop shall comply with the following provisions:


1) all kinds of pipes, automatic fire fighting equipment, air conditioning purification machine equipment (central air conditioning, centrifugal fan, clean refrigeration unit, high efficiency air filter (function: overthought residue, etc.), stainless steel air shower, etc.) installation should be appropriate, strong, strict, error should meet the relevant requirements;


2) ordinary high school air filter (function: overworry residue, etc.) and fixed bracket connection, ventilation duct and machine equipment connection should be reliable tightness;


3) All kinds of adjustment equipment should be strict, convenient and convenient in practice;


4) There is no dust in the central air conditioning, plenum, ventilation duct system software and air supply outlet of the purification workshop;


5) The walls, ceiling ceiling surface and road surface in the purification workshop should be levelled and well-colored, and the road surface should be free of dust and electrostatic induction (electrostatic induction);


6) Air supply, air supply, a variety of tail equipment, a variety of pipelines, lighting fixtures and transmission line pipelines, technology according to the purification room, the sealing solution at the junction should be strict and reliable;


7) All kinds of distribution boxes, cabinets and electrical equipment pipelines and branch pipes into the purification room of the purification workshop should be reliable tightness. The principle of purification room workshop purification is that when the control panel is connected to the switching power supply, the port of the oil mist separator causes strong negative pressure, which causes the welding smoke to be inhaled. The separator impacts under the effect of the impeller, so that the fine particles gather into controllable small particles, and the gas and water realize the separation of oil and water under the barrier of the high-efficiency fog-absorbing raw materials. Purification workshop indoor temperature air dust removal, high temperature air filtration, air purification, station ash removal.